Bid Results

2018 Bid Results

Wilkshire Hills WWTP Headworks Improvement Project

Contractor

Bid Category

Bid Amount

Stanley Miller Construction Base Bid $746,396.00
  Alternate - Wet Well Repair $40,810.00
  Alternate - Dry Well Repair $81,083.00
  Alternate - Influent Pump VFDs $47,234.00

The Base Bid amount exceeds 10% of the Engineer's Estimate, and in accordance with Ohio Revised Code, the project cannot be awared.  The District plans to seek additional funding to proceed with the project and plans to re-bid later this year or early 2019.